Upgrade of the customs clearance facilities at the road Border Crossing Tabanovce and supervision of works

Project facts:

Objective: expansion and adaptation of the existing import/export terminal for additional 4,000 m2 construction of two lanes at the BCP – exit from the Republic of Macedonia; construction of supporting facilities..

Duration: : 24 months (start 4 quarter of 2016, ending 4th quarter of 2017, with warranty period until 4th quarter of 2018)

Value: EUR 1.85 million

Outcome: Improved infrastructure of the BCP and increasing the flow at the BCP, the time required to complete border formalities has been reduced, enabling the application of modern means of inspection, speeding up and facilitating trade, facilitating and speeding up transport along the Pan-European corridors 8 and 10.

Scroll to top

.

logo footer

The contents of this page may be published without special permission by indicating the source. Any intrusion or abuse on the website of the Customs Administration is penalized under the Article 251 of the Criminal Law..